Alert

Chatham Twp, 2024 Road Maintenance Schedule Announced

From the Township of Chatham, NJ - 

As part of the Township of Chatham’s commitment to providing the best services possible and ensuring infrastructure is maintained to highest levels, Mayor Stacey Ewald and the Township Committee adopted Resolution 2024-153 on June 25, 2024 to authorize the award of a road resurfacing contract to Riverview Paving, Inc. in an amount not to exceed $475,000. Additionally, the Township was awarded a grant from the State of New Jersey in the amount of $260,630 for improvements to River Road (from Southern Boulevard to the Township Boundary) and Mount Vernon Avenue.

The roads were selected based on the professional recommendations of the Township Engineer and Public Works Superintendent. Township roads are evaluated and assessed annually based on a number of criteria. An annual repaving list is then developed that considers the total length of road resurfacing possible within the annual budget allocation and the score/grade of the municipal roads.

A pre-construction meeting was held on July 16, 2024 with Township staff and the contractor. The contractor provided the milling and paving schedule below. Please note that this schedule is subject to change and may be affected by weather.

Street Date of Milling Date of Paving
Oak Hill Road July 31 August 6
Woodmont Drive July 31 August 6
Southward Court August 1 August 6
Conger Terrace August 1 August 7
Garden Street August 1 August 7
Mitchell Avenue August 1 August 7
Gates Avenue August 2 August 7
Stafford Road August 2 August 8
Mount Vernon Avenue August 2 August 8
River Road August 5 August 9
Valley View Road August 7 August 12
Club Road August 7 August 12